Presentations by the firms for RFQ#14-010 Ocean Park Revitalization Plan - Phase I
CITY OF DANIA BEACH
Agenda Request Item
Type of Request: Presentation
(Adopt Resolution, Adopt Ordinance (1st Reading) Adopt Ordinance (2nd Reading)
Award Bid /RFP, Presentation, Public Hearing)
Requested Action (Identify appropriate Action or Motion) |
The RFQ-#14-010 Ocean Park Revitalization Plan – Phase I, was advertised on May 2, 2014. The Request for Qualifications (RFQ) were submitted by respondents on Friday, May 23, 2014. Responses to the RFQ were submitted by EDSA, Kimley-Horn & Associates and BEA Architects, Inc. |
Description of Action |
The Review Committee, consisting of Marc LaFerrier, Director of Community Development, Colin Donnelly, Assistant City Manager, Ronnie Navarro, Engineer, Mark Felicetty, Director of Parks and Recreation and Yeimy Guzman, Controller. The Committee met on Wednesday, May 28, 2014 to review and evaluate the RFQs that were submitted to the City. The following are the combined scores from the committee members for each respondent:
TEAM TOTAL SCORE • BEA Architects, Inc. 224 • EDSA 360 • Kimley-Horn & Associates 235 |
Purchasing Requests ONLY |
||
Fund: (Select from: General, Water, Sewer, Stormwater, Grants, Capital) |
Fiscal Impact/Cost Summary |
Exhibits Attached |
|
Memo |